Live projectApex Aura Society — Tower F, Towers I & J
Execution and project control on Tower F — shuttering and slab work with the firefighting scope; Towers I & J modelled in 3D from the brochure unit plans.
- Programme
- 22 weeks, April – September 2026
- RCC scope
- Excavation, PCC, reinforcement, slab shuttering
- Services scope
- MEP sleeve pre-embedment · IS:1239 firefighting risers · sprinkler & detection · testing and commissioning
- Control
- BBS-controlled steel with wastage held at 1.8% · IS:456 pour cards before every pour · GPS-tagged DPR at 19:00 every site day
- Reporting
- Weekly progress report with planned-vs-actual, earned value (SPI / CPI / EAC), RFI log, NCR register, material reconciliation, risk register and photo log